General Abstract B2V2:

Sector-Wise Abstract (Physical/Financial) of B2V2 Programme 2020-21  (District Kulgam)  (Rs in lakhs)
S No Name of the Sector No of works authorized under B2V2 No of works completed Under progress Total Funds released under B2V-2 Expenditure under B2V-II ending 03/2021 Expdtt %age
Ongoing New Total 
1 RDD 14 52 66 66 0 66 166.307 157.071 94.45
2 PHE 7 0 7 6 1 7 11.934 10.934 91.62
3 Irrigation 0 5 5 4 1 5 18.796 8.756 46.58
4 Flood Control 0 2 2 2 0 2 28.233 25.030 88.66
5 PDD 0 5 5 5 0 5 24.730 24.08 97.35
Total 21 64 85 83 2 85 250.000 225.866 90.35
  1. Rural Development Department:
Physical and Financial Progress Report under B2V-II                                                         (Rs in lakhs)    
S No Block Panchayat Halqa Type Name of the work Authorised cost Rs in Lacs Cummu Expdtt ending 03/2020  funds released  under B2V2  2020-21 Expdt. Under B2V2 (ending 02/2021) Physical Status
BTV2 14th FC MGNREGA Total
1 Pombay Gopalpora ongoing C/o. road from Graveyard to HO Tayoub Shah via Parry Mohalla Gopalpora 2.300 2.29 0.66 5.250 0.00 2.3000 2.3000 Completed
2 Pombay Mirhama ongoing C/o. Mirhama to Laisoo road. 2.875 2.88 1.60 7.350 0.00 2.8750 2.8750 Completed
3 Pombay Nillow New C/o. different lanes and roads at Panchayat Halqa Nillow 6.000 0.00 1.50 7.500 0.00 6.0000 6.0000 Completed
Total Pombay 11.18 5.17 3.76 20.10 0.00 11.18 11.1750  
1 Kund Kanchloo New Const. of  road  connectivity in interior of GP Panchayat Halqa Kancloo Block Bund 6.000 0.00 1.50 7.500 0.000 6.0000 5.2900 Completed
Total Kund 6.00 0.00 1.50 7.50 0.00 6.00 5.29  
1 Kulgam Awhatoo ongoing Construction / up-gradation of internal roads at Awhatoo 0.870 0.870 2.200 3.940 0.000 0.8700 0.8700 Completed
2 Kulgam Checkpora New Restoration of Irrigation Channel at Checkpora   1.600 0.000 0.400 2.000 0.000 1.6000 1.6000 Completed
3 Kulgam Okey New C/o. Filling, fencing and drainage system for play ground at Okey 4.000 0.000 1.000 5.000 0.000 4.0000 0.0000 Phy completed
4 Kulgam Amanoo New C/o. Road from Amanoo to Shurat . 2.400 0.000 0.600 3.000 0.000 2.4000 2.4000 Completed
5 Kulgam Nanibugh New C/o. Link road from Nanibugh to Primary School Towards Poniwah. (Rural Connectivity) 2.400 0.000 0.600 3.000 0.000 2.4000 2.4000 Completed
6 Kulgam Shurath New C/o Link road from Jamia Masjid Dadipora to H/O Ab Salam Rather 4.000 0.000 1.000 5.000 0.000 4.0000 4.0000 Completed
7 Kulgam Bougam A New C/o Bund over Kralnard near Nazir Ahmad Mir Kumar Mohalla  2.000 0.000 0.500 2.500 0.000 2.0000 2.0000 Completed
8 Kulgam Ashthal New C/o. Flood Protection bund Nindeth to Veshu North South for Ashthal 4.000 0.000 1.000 5.000 0.000 4.0000 4.0000 Completed
9 Kulgam Awgam New C/o. Road at Bundal Awgam 2.800 0.000 0.700 3.500 0.000 2.8000 2.8000 Completed
10 Kulgam Bugam B New C/o. drainage system at PHC 2.400 0.000 0.600 3.000 0.000 2.4000 0.0000 Phy Completed
11 Kulgam Katrasoo New C/o. foot road upto the spot Razakun at Katrasoo 2.240 0.000 0.560 2.800 0.000 2.2400 2.2400 Completed
12 Kulgam Chansar New C/o. Lane / Street at New Mohalla Kandri from main road to Mubarik Ahmad Rather 1.600 0.000 0.400 2.000 0.000 1.6000 1.6000 Completed
13 Kulgam Sangus  New C/o road Lamman to Batsargam via Kharote Sangus 1.200 0.00 0.80 2.000 0.000 1.2000 1.2000 Completed
14 Kulgam Tazipora  New C/o FP Bund around the Nalla Grumath 1.450 0.00 0.85 2.300 0.000 1.4500 1.4500 Completed
Total Kulgam 32.96 0.87 11.21 45.04 0.00 32.96 26.56  
1 D.H Pora Nandimarg-A ongoing C/o road / lane  at Nandimarg. 1.605 1.605 0.910 4.120 0.000 1.6050 1.605 Completed
2 D.H Pora Ahamadabad A ongoing C/o. road from Beigh Mohalla to Ziyarat Sharieef Ali Shah Saheb Laispora. 1.160 1.000 0.500 2.660 0.000 1.1600 1.160 Completed
3 DH Pora Yarikhah C New Constt. of concrete Bund on Nallah Kandi from Ganie Mohalla to Kooli Mohalla at Yarikhah C  4.000 0.000 1.000 5.000 0.000 4.0000 4.0000 Completed
Total DH Pora 6.77 2.61 2.41 11.78 0.00 6.77 6.765  
1 Qaimoh Danow ongoing C/o. New road from Makanpora to Wazirpora and Wazirpora to Shiekhpora. 2.500 2.500 2.500 7.500 0.000 2.5000 2.4000 Completed
2 Qaimoh Redwani Payeen ongoing C/o. Internal drainage system at Redwani Payeen 1.800 1.220 1.980 5.000 1.000 0.8000 0.7700 Completed
3 Qaimoh Bogund New Up-gradation of Interior  roads at Bogund. 4.000 0.000 1.000 5.000 0.000 4.0000 4.0000 Completed
4 Qaimoh Buchroo New Renovation of Irrigation Khul main road to HO Ab Satar Bhat in Village Wazirpora 2.400 0.000 0.600 3.000 0.000 2.4000 2.4000 Completed
5 Qaimoh Qaimoh New C/o. Passenger shed at main Chowk Qaimoh  2.400 0.000 0.600 3.000 0.000 2.4000 2.4000 Completed
6 Qaimoh Sonigam New C/o. Tile lane from main road to Shop of Mushtaq Ahmad Itoo at Her Sonigam. 2.400 0.000 0.600 3.000 0.000 2.4000 2.4000 Completed
7 Qaimoh Tarigam New Dev. of Link road from HO Nazir Ahmad Mir to Kawan 4.000 0.000 1.000 5.000 0.000 4.0000 4.0000 Completed
8 Qaimoh Rehpora New C/o. link road with drain from Gull Dar to Paddy field of Muzafar Dar 2.800 0.000 0.700 3.500 0.000 2.8000 2.8000 Completed
9 Qaimoh  Wanigund  New Upgradation of link road from main road to Govt Middle School at Wanigund. 3.000 0.00 1.00 4.000 0.000 3.0000 2.8600 Completed
10 Qaimoh  Kawaki Bazar New C/o drainage system at Kawaki Bazar  1.200 0.00 0.80 2.000 0.000 1.2000 0.8239 Completed
11 Qaimoh  Matalhama New Upgradation of internal roads at Mutalhama 1.200 0.00 0.80 2.000 0.000 1.2000 1.2000 Completed
Total Qaimoh 27.70 3.72 11.58 43.00 1.00 26.70 26.054  
1 Pahloo Shahoo Sachan ongoing C/o. Lining wall / protection wall on both sides of  Sachen Ladh from source.  1.085 1.085 1.860 4.030 0.000 1.0850 1.0850 Completed
2 Pahloo Malwan B ongoing C/o road to uncovered habitations Tangwani and Vendor and Gujjar Basti 1.750 2.000 0.650 4.400 1.143 0.6070 0.6070 Completed
3 Pahloo Lammer B New C/o. Road from Hallan Adda to Kotpath( full road connectivity)   4.000 0.000 1.000 5.000 0.000 4.0000 4.0000 Completed
4 Pahloo Banimullah New C/o. Road connectivity to Gojar Basti KharporaBanimullah 2.400 0.000 0.600 3.000 0.000 2.4000 2.4000 Completed
Total Pahloo 9.24 3.09 4.11 16.43 1.14 8.09 8.09  
1 Manzgam Avil ongoing Levelling of Play Field at Govt M/S Avil P/H Avil. 2.090 0.000 1.180 3.270 0.000 2.0900 2.0500 Completed
2 Manzgam Hallan ongoing C/o. lane / steps with covered roof from Manzgam to Hallan P/H Hallan 2.500 2.000 0.960 5.460 0.000 2.5000 2.5000 Completed
3 Manzgam KB Pora A ongoing C/o. road from main road to Singora via Nowbugh P/H KB Pora A. 2.500 2.000 3.880 8.380 0.000 2.5000 1.1500 Completed
4 Manzgam Chowgalpora New C/o. drain  at Chowgalpora 1.600 0.000 0.400 2.000 0.000 1.6000 1.6000 Completed
5 Manzgam Wattoo A New C/o. road from Panchayat to Hergam. 4.000 0.000 1.000 5.000 0.000 4.0000 4.0000 Completed
6 Manzgam Wattoo B New C/o. link road from main road to Jumma Thokerepra via Noorul Islam Public School at Checki Wattoo. 4.000 0.000 1.000 5.000 0.000 4.0000 4.0000 Completed
Total Manzgam 16.69 4.00 8.42 29.11 0.00 16.69 15.30  
1 DHK Marg Dragdan ongoing C/o. Batpora Palpora road  1.445 1.445 0.00 2.890 0.000 1.4450 1.4450 Completed
2 DHK Marg Boh New C/o. Linning wall of Boshi Nallah from Kandimarg to DK Marg Bridge via Boh 4.000 0.000 1.00 5.000 0.000 4.0000 3.9200 Completed
3 DHK Marg Nagam  A New C/o. Fencing around Eidgah Mirpora and fencing around High School Nagam 4.000 0.000 1.00 5.000 0.000 4.0000 4.0000 Completed
4 DHK Marg Chimmer B New Construction of road from Dumpora to Naibasti at Chimmer-B DK Marg 3.000 0.000 0.00 3.000 0.000 3.0000 2.9900 Completed
Total DK Marg 12.45 1.45 2.00 15.89 0.00 12.45 12.355  
1 Devsar Bonigam New C/o. Fencing of New Eidgah at Bonigam 2.400 0.000 0.60 3.000 0.000 2.4000 2.4000 Completed
2 Devsar C Panjan New C/o. FP Bund alongside River Nallah Yethyethru 4.000 0.000 1.00 5.000 0.000 4.0000 4.0000 Completed
3 Devsar Khrewan New C/o. FP Bund on Veshue Nallah at Lassipora 4.000 0.000 1.00 5.000 0.000 4.0000 4.0000 Completed
4 Devsar Bozgam New C/o. drain  at through Village Aagroo 5.600 0.000 1.40 7.000 0.000 5.6000 5.6000 Completed
5 Devsar YH Babapora New C/o Irrigation Ladh from Bonigam to Baihama 4.000 0.000 1.00 5.000 0.000 4.0000 4.0000 Completed
Total Devsar 20.00 0.00 5.00 25.00 0.00 20.000 20.00  
1 Behibagh Hanjan New Dev. of link from Hanjan to Shiganpora to Daderkote. 4.000 3.64 2.36 10.000 1.720 2.2800 2.2800 Completed
2 Behibagh Yamrach -A  New Upgradation of link roads at Yamrach 1.200 0.000 0.80 2.000 0.000 1.2000 1.2000 Completed
3 Behibagh Parigam  New C/o fencing of graveyard near Ziyarat Sharief  1.200 0.000 0.80 2.000 0.000 1.2000 1.2000 Completed
4 Behibagh Hangalbush  New C/o tile lanes in Gram Panchayat  1.200 0.000 0.80 2.000 0.000 1.2000 1.2000 Completed
5 Behibagh Daderkoot  New C/o link road at Nadbal Cheki Hanjan, Ganie Mohalla Daderkoot, Sofipora & Cheki Hanjan Wanipora Nowpora  1.200 0.000 0.800 2.000 0.000 1.2000 1.2000 Completed
6 Behibagh Tantraypora  New Upgradation of link roads at various spots, Shahpora Sonikhah Sehpora  1.200 0.000 0.800 2.000 0.000 1.2000 1.2000 Completed
7 Behibagh Yamrach – B New C/o road network to field crop at Yamrach  1.200 0.000 0.800 2.000 0.000 1.2000 1.2000 Completed
8 Behibagh Munad Gufan New C/o road from Middle School towards Hatipora Batpora  1.200 0.000 0.800 2.000 0.000 1.2000 1.2000 Completed
9 Behibagh Matibugh  New C/o lin road from main road to Beebrada with edge walls at Matibugh  1.200 0.000 0.800 2.000 0.000 1.2000 1.2000 Completed
10 Behibagh Sempora Derpora  New C/o road from Tungdanoo Masjid Sharief to Munchwa  1.200 0.000 0.800 2.000 0.000 1.2000 1.2000 Completed
11 Behibagh Khee Jogipora  New C/o link road from main road Jogipora to Kumar Mohalla  1.200 0.000 0.800 2.000 0.000 1.2000 1.2000 Completed
12 Behibagh Noonmai New Const. of approach road to SSA School and Marg. 4.000 0.00 1.00 5.000 0.000 4.0000 4.0000 Completed
13 Behibagh Turigam New C/o Link raod Turigam Devbugh to Nanibugh. 3.200 0.00 0.80 4.000 0.000 3.2000 3.2000 Completed
Total Behibagh 23.20 3.64 12.16 39.00 1.72 21.480 21.48  
1 Frisal Badroo New C/o. Link road from Salfia School to Lanchi Wouder at Badroo. 4.000 0.000 1.00 5.000 0.000 4.0000 4.0000 Completed
Total Frisal 4.000 0.000 1.000 5.000 0.000 4.000 4.000  
Grand Total 170.170 24.530 63.150 257.850 3.863 166.31 157.071  

 

2. Public Health Engineering (PHE):

List of works executed/ under execution under Back to Village Programme – 2nd Phase      
S No Sector/
Agency
Panchayat Halqa Name of the work Estimated Cost Authorised cost Rs in Lacs Funds released under B2V1 during 2019-20 Expdt. 31-03-2020 funds released  under B2V2 during 2020-21 Expdtt during 2020-21 (B2V2) Physical Status Remarks
BTV 14th FC MGNREGA Total BTV 14th FC MGNREGA Total
1 PHE Akhall Providing & fixing of chain link fencing around 0.10 Lac gallon collection sump and spring at Akhall WSS Akhall 10.00 10.00 0.000 0.000 10.000 4.36 4.36 0.00 0.00 4.36 5.640 4.640 70% completed 1.00 Surrender
2 Waltengoo Up-gradation and extension of outlived/undersized supply and distribution system of WSS Kraloo & Waltengoo. 8.00 8.00 0.000 0.000 8.000 7.18 7.18 0.00 0.00 7.18 0.770 0.770 Completed  
3 Ashmuji-A L/F of Parrallel line from SR upto Mohalla Mishpora Ashmuji-A 7.00 7.00 0.000 0.000 7.000 5.77 5.77 0.00 0.00 5.77 0.372 0.372 Completed  
4 Hallan Providing of drinking water supply to village Hallan 4.00 4.00 0.000 0.000 4.000 2.53 2.53 0.00 0.00 2.53 1.102 1.102 Completed  
5 Shirpora Restoration of drinking water supply facilities to Shirpora 9.00 9.00 0.000 0.000 9.000 8.11 8.11 0.00 0.00 8.11 0.000 0.000 Completed  
6 Manzgam Upgradation of RS at Manzgam B 1.76 1.50 0.000 0.000 1.500 1.28 1.28 0.00 0.00 1.28 0.000 0.000 Completed  
7 Bangward Construction of 0.12 lac gallon capacity SR for village Bangward 4.33 3.78 0.000 0.000 3.780 3.78 0.00 0.00 0.00 0.00 3.750 3.750 Completed  
8 Tangmarg-A Laying/fitting of 40mm dia supply line Rather Mohalla Tangmarg 1.00 1.00 0.000 0.000 1.000 0.65 0.65 0.00 0.00 0.65 0.300 0.300 Completed  
    Total PHE  45.09 44.28 0.00 0.00 44.28 33.66 29.88 0.00 0.00 29.88 11.93 10.934    

3. Irrigation:

List of works under execution under Back to Village Programme – 2nd Phase    
S No Sector/
Agency
Block Panchayat Halqa Name of the work Estimated Cost Authorised cost Rs in Lacs Funds released under B2V1 during 2019-20 Expdt. 31-03-2020 Funds released  under B2V2 during 2020-21 Expdtt during 2020-21 (B2V2) Physical Status
BTV 14th FC MGNREGA Total BTV 14th FC MGNREGA Total
1 Irrigation Qaimoh Rampora Restoration of damaged escape channel of Durbal Ladi ( B/o Mav Khul)  at  Hawoora.  2.00 2.00 0.000 0.000 2.000 0.80 0.80 0.00 0.00 0.80 1.200 1.200 Completed
2 Behibagh Behibagh Construction of cement concrete channel near the delivery tank of Behibagh LIS at village Behibagh spot 2nd. 4.50 4.5 0.000 0.000 4.500 0.00 0.00 0.00 0.00 0.00 2.980 2.980 Completed
3 Behibagh Katapora Construction of lining wall on both sides of Katapora Minor from Khanpor Check to Zainpora canal at places. 4.90 4.90 0.000 0.000 4.900 0.00 0.00 0.00 0.00 0.00 3.266 3.266 Completed
4 Kulgam   Construction of Tractor Crossing /foot bridge at RD 10150 Mtr on Mav Kull at village Poniwah 11.976 11.976 0.000 0.000 11.976 0.00 0.00 0.00 0.00 0.00 8.840 0.000 Under Progress
5     C/o Irrigation Canal from Goniwan to Konchipora by way of Construction of R/Wall and bed treatment 3.154 3.154 0.000 0.000 3.154 0.00 0.00 0.00 0.00 0.00 2.510 1.310 Completed
    Total Irrigation 23.38 23.38 0.00 0.00 23.38 0.80 0.80 0.00 0.00 0.80 18.80 8.756  

4. Flood Control:

List of works  executed under Back to Village Programme – 2nd Phase    
S No Sector/
Agency
Panchayat Halqa Name of the work Estimated Cost Authorised cost Rs in Lacs Funds released under B2V1 during 2019-20 Expdt. 31-03-2020 funds released  under B2V2 during 2020-21 Expdtt during 2020-21 (B2V2) Physical Status
BTV 14th FC MGNREGA Total BTV 14th FC MGNREGA Total
1 Flood Control Cluster of Panchayats Construction of Protection bund from Nihama bridge to Water Tank Nihama (RD 10600-10890 Mtrs)with spurs 17.027 17.027 0.000 0.000 17.027 0.00 0.00 0.00 0.00 0.00 17.027 16.530 Completed
2 Cluster of Panchayats Construction of FP Bund on L/S of Veshow Nallah at Naid Pora Chadder 11.973 11.973 0.000 0.000 11.973 0.00 0.00 0.00 0.00 0.00 11.206 8.500 Completed
    Total Flood Control 29.00 29.00 0.00 0.00 29.00 0.00 0.00 0.00 0.00 0.00 28.233 25.03  

5. PDD:

List of works under execution under Back to Village Programme – 2nd Phase    
S No Sector/
Agency
Block Name of the work Estimated Cost Authorised cost Rs in Lacs Funds released under B2V1 during 2019-20 Expdt. 31-03-2020 funds released  under B2V2 during 2020-21 Expdtt during 2020-21 (B2V2) Physical Status
BTV 14th FC MGNREGA Total BTV 14th FC MGNREGA Total
1 PDD Kulgam Providing of 63KV transformers for meeting out B2V demands  5.00 5.000 0.000 0.000 5.000 5.000 0.00 0.00 0.00 0.00 5.00 4.950 Completed
2 PDD Pombay Construction of 63KVA Substation at Bonpora Naibasti Nehama 2.65 0.000 0.000 0.000 2.650 0.000 0.00 0.00 0.00 0.00 2.65 2.620 Completed
3 PDD Kulgam Construction of 100 KVA Substation at Bomrath Mohalla new Basti 4.80 0.000 0.000 0.000 4.800 0.000 0.00 0.00 0.00 0.00 4.80 4.790 Completed
4 PDD Devsar HT/LT improvement at village Chandian Panjan NHO Sabzar Ahmad Malik 2.50 0.000 0.000 0.000 2.500 0.000 0.00 0.00 0.00 0.00 2.50 2.500 Completed
5 PDD Behibagh Creation of 63 KVA Substation at Naid Hanjan 3.00 0.000 0.000 0.000 3.000 0.000 0.00 0.00 0.00 0.00 3.00 2.805 Completed
6 PDD   Construction of 63KVA Substation at Arreh Bangladash New Colony 3.00 0.000 0.000 0.000 3.000 0.000 0.00 0.00 0.00 0.00 3.00 2.990 Completed
7 PDD   Creation of 100 KVA Substation alongwith HT line at Bonpora Badroo 3.78 0.000 0.000 0.000 3.780 0.000 0.00 0.00 0.00 0.00 3.78 3.420 Completed
    Total PDD 24.73 5.00 0.00 0.00 24.73 5.00 0.00 0.00 0.00 0.00 24.73 24.08