LANGUISHING PROJECTS

Abstract of status of Projects approved for funding through JKIDFC in District Kulgam                                                                                                                                                                                              ( Rs. in Lakhs).
S. No Sector Type of Construction approved No. of Projects Approved Cost (JKIDFC) Funds released Status of Bills uploaded Expdtt. (Ending 03/2021) Completion status
No of Bills Amount 100% Above 50% to 90% Upto 50%
1 R&B Bridges 11 2732.68 920.73 19 937.25 920.73 7 3 1
Roads 10 4204.99 398.76 8 439.77 398.76 2 3 5
Buildings 2 465.99 167.57 5 186.20 167.57 0 2 0
Total R&B 23 7403.66 1487.06 32 1563.22 1487.06 9 8 6
2 PHE WSS 34 4526.82 803.14 207 1155.76 803.14 14 13 7
3 Health Buildings 13 2503.93 689.05 13 689.05 689.05 1 6 6
4 PDD Sub stations  4 565.24 0.00 5 22.45 0.00 0 2 2
5 Higher Education  Buildings 1 882.78 0.00 0 0.00 0.00 0 0 1
6 School Education Buildings=03,
WSS=01 (71 Schools)
4 191.63 89.06 6 101.87 89.06 0 3 1
7 Technical Education Buildings 1 82.00 0.00 0 0.00 0.00 0 0 1
9 YSS Play Field, 20 602.98 74.00 8 102.30 74.00 4 4 12
10 Animal & Sheep Husbandry  Buildings 1 5.00 4.60 4 4.60 4.60 1 0 0
11 H&UDD Buildings 1 53.41 13.76 1 13.76 13.76 0 0 1
12 Irrigation Irrigation Canal (Sonman) 1
(57 spots)
407.04 258.26 57 307.84 258.26 1 0 0
Total 103 17224.49 3418.93 333 3960.85 3418.93 30 36 37

 

Status of Languishing Projects of District Kulgam approved for funding  through JKIDFC                                                                                                                                                                   Rs. in lacs 
S. No Nomenclature of the Project Executing Agency Approved cost through JKIDFC Funds released through JKIDFC No. of Bills uploaded on Portal Expdtt. (Ending 03/2021) Present Physical Status
 ( of balance work)
Timeline for completion
No  Amount
R&B Sector
1 Construction of  1×12 Mtr span bridge in KM Ist on Adipora Mishpora Road. R&B 46.80 41.73 2 46.37 41.73 100% Completed  
2 Construction of  1×10 Mtr span bridge on Khudwani Ganjipora Road. R&B 83.84 57.70 3 64.12 57.70 100% completed:  
3 Construction of 1×10 Mtr span bridge at Chinigam Frisal R&B 56.65 50.42 4 56.02 50.42 100% Completed:   
4 Construction/ Upgradation of Labdipora Laroo Byepass road incld: industrial road  with allied links (5.35 Km) R&B 475.25 0.00 0 0.00 0.00 2% Completed
(Earth work RBM=0.30 KM) (land/structure compensation required)
Sep-21
5 Construction of Nandimarg Gulabgrah road (9.00 Kms phase-I) R&B 788.22 111.57 3 123.97 111.57 35% completed:  
06 Mtr span in KM 1st  partly completed, Earth work 3.0 KM, RBM=2.50 KM completed)
Sep-21
6 Upgradation of Nillow Begam road incld: Nillow Awahatoo road (Length 4.00 Kms) R&B 162.59 49.62 2 55.14 49.62 47% Completed:  WBMG-III = 2.00 KM completed, Macadamised=1.60 Km completed Sep-21
7 Construction/Upgradation of Kulgam Chatabal   Panipora Kutbal Ban Kandipora road (Length 5.00 Kms) R&B 96.39 0.00 0 0.00 0.00 5% completed:  
Earth work=0.25 KM completed, P/L of WBMG II=0.40 KM completed
Sep-21
8 Construction of PWD Complex at Tsawalgam Kulgam R&B 358.75 115.06 3 127.85 115.06 70% completed:
Structure & walling completed, finishing items in progress. 
Mar-21
9 Constt. Of Bogund Kulpora Road R&B 105.36 66.96 2 74.41 66.96 100% completed  
10 Constt. /Upgradation of Shirpora Baldara including Frisal Ziyarat Ayar and Frisal Shedcheck road R&B 64.94 37.49 2 41.65 37.49 96% completed:
Earth work, RBM/G-II=1.08 KM , Macadam=1.04 KM completed
Nov-20
11 Up-gradation of Gandwani-Jaibal including C.R.Pora Road (6.20 KMs) R&B 145.10 102.11 4 113.45 102.11 100% completed  
12 Construction City retreat at Kutbal Kulgam R&B 107.24 52.51 3 58.35 52.51 70% completed:
Structure completed, finishing and sanitary items partly completed.
Dec-20
13 Construction of 2×30 Mtr span steel girder bridge on Nallah Vethvetroo at Babapora. R&B 293.98 287.59 2 287.59 287.59 100% Completed  
14 Construction of 1x30mtr span steel girder Jeepable foot bridge at Amanpora. R&B 118.73 107.49 2 107.49 107.49 100% Completed  
15 Constr; of 2 x20 Mtr  span bridge at Bona  Manigam Chanderkote  (Redesigned as 1×40 Mtr span bridge) R&B 13.00 0.00 0 0.00 0.00 85% Completed:
Slab for bridge completed.
Mar-21
16 Constt. Of approach road including  constt. Of 1×30 mtr span steel decked bridge near 11×30 mtr. Span steel trussed bridge over Nallah Vishow on proposed road from Kilam Gund to Ashmuji Kulgam. R&B 444.30 151.95 2 151.95 151.95 70% Completed:  
1×30 Mtr span bridge is in progress and approaches road in progress
Jun-21
17 Constt. Of 1×30 mtr. Span steel trussed bridge over Nallah Kralookund in km 2nd of Kraloo Uril road. R&B 94.39 84.25 2 84.25 84.25 100% Completed  
18 Constt. Of 1×30 span steel trussed bridge over kraloo Nallah in Km 1st of YK Pora to Batnagoo via Peer Takiya road R&B 108.17 96.97 2 96.97 96.97 100% Completed  
19 Constt. Of 1×30 Mtr span jeepable foot bridge at Hakradan Waripora Kund over Nallah Khider/Budkhul R&B 144.73 45.94 2 45.94 45.94 90% Completed:
Sub-structure completed, girders launched , slab laid.
Dec-20
20 Construction /Upgradation of Waltengoo Vasaknag road R&B 190.51 27.71 1 27.71 27.71 50% Completed
(Earth work=1.30 KM, GSB=1.40 KM,
Grade-II=1.60KM)
Mar-21
21 Widenining /Upgradation of Munand-Alamgunj-Dadekoot-Chancer-Kulgam road R&B 1309.50 0.00 0 0.00 0.00 Work in Progress  
22 Construction  of 7×42+1x48Mtr+ 1x30Mtr+ Bridge on Pombay Adijan  Damhal Road Kulgam   R&B 1328.09 0.00 0 0.00 0.00 70% work completed  
23 Up-gradation of Khudwani-Nowbal-Arwani road including interior roads R&B 867.13 0.00 0 0.00 0.00 Work in Progress  
Sub Total R&B   7403.66 1487.06 32 1563.22 1487.06    
PHE Sector
1 WSS Damhal PHE 91.10 6.17 10 14.45 6.17 100% Completed  
2 WSS Vovrikull PHE 90.70 34.00 4 34.00 34.00 100% Completed  
3 WSS Hakwas KB Pora  PHE 128.20 0.00 7 25.04 0.00 100% Completed  
4 WSS Nardpora Autto PHE 74.33 16.87 13 38.63 16.87 70% Completed (Proc. Of pipes=100%, L/F=70%, SR=60%, FP=20%, PST=30%, CF=20%) Oct-20
5 WSS Challan Narsingpora PHE 155.76 32.70 13 56.24 32.70 50% Completed (Proc. Of pipes=100%, L/F=40%, SR=40%, Fencing=10%) Oct-20
6 WSS Laisoo PHE 108.33 0.00 11 63.04 0.00 50% Completed (Proc. Of pipes=100%, L/F=60%, SR=15%, FP=10%, PST=10%, CF=20%) Oct-20
7 WSS Zrode Gujjerbasti PHE 132.41 81.36 2 81.36 81.36 60% Completed (Proc. Of pipes=100%, L/F=60%, SR=100%) Dec-20
8 WSS Doie Mohalla Gulabpathri PHE 59.91 9.24 8 29.39 9.24 70% completed (Proc. Of pipes=100%, SR=100%, L/F=70%, PST= 10%) Sep-20
9 WSS Pazipora PHE 72.27 26.35 9 33.32 26.35 70% Completed (Proc. Of pipes=100%, L/F=60%, SR=100%, FP=10%, PST=10%, C/F=60%) Oct-20
10 WSS Nassu PHE 38.01 15.16 15 29.56 15.16 85% Completed (Proc. Of pipes=100%, L/F=100%, SR=70%, PST=100%) Oct-20
11 WSS Widow Mishpora PHE 142.07 0.00 8 42.42 0.00 70% Completed (Proc. Of pipes=100%, L/F=70%, SR=90%)  Dec-20
12 WSS Yaripora PHE 53.70 22.88 9 34.95 22.88 100% Completed  
13 WSS Brazloo Tengen PHE 249.25 80.03 12 84.76 80.03 60% Completed (Proc. Of pipes=100%, L/F=60%, PST=95%, Intake Chamber=95%) Dec-20
14 WSS Chandergee PHE 45.00 15.27 8 19.12 15.27 100% Completed  
15 WSS Sonigam PHE 44.60 28.62 5 36.22 28.62 100% Completed  
16 WSS Gofbal Kawaki Bazar PHE 60.00 19.90 3 19.90 19.90 70% Completed  (Proc. Of pipes=100%, L/F=60%,CF=60%)  Oct-20
17 WSS Soper Danew PHE 58.50 36.81 4 36.81 36.81 100% Completed  
18 WSS Malwan Gujjer basti PHE 36.18 27.87 6 27.87 27.87 100% completed  
19 WSS Budroo Demmbdulla PHE 55.60 2.60 3 9.47 2.60 100% Completed  
20 WSS Shalipora Tarigam PHE 75.20 20.71 4 20.71 20.71 100% Completed   
21 WSS Sarsuan Tantrypora PHE 90.30 0.00 2 12.68 0.00 100% Completed  
22 WSS Banimullah Gujar Basti PHE 106.86 27.30 5 33.10 27.30 70% completed (Proc. Of pipes=100%, L/F=0%, CF=100%, SR=100%, Pump House-1st=100%) Oct-20
23 WSS Up-gradation of Kulgam Town PHE 403.67 203.28 17 254.05 203.28 50% completed (Proc. Of pipes=60%, L/F=50%, 3 No. SR=100%, CF=100%, 2No. PST=100%) Dec-20
24 WSS Nillow PHE 341.50 0.00 0 0.00 0.00 0% Mar-21
25 WSS Kadder Turigam PHE 787.00 0.00 0 0.00 0.00 0% Mar-21
26 WSS Hadigam PHE 351.00 0.00 0 0.00 0.00 0% Mar-21
27 WSS Sangus Kaharwat PHE 372.00 0.00 0 0.00 0.00 0% Mar-21
Total Kulgam Division   4223.45 707.12 178.00 1037.09 707.12    
28 Augumentation of Razloo WSS PHE 47.37 23.08 4 24.28 23.08 100% Completed
 (work on fencing is in progess)
 
29 WSS Gundi Tankipora PHE 16.86 0.00 3 11.17 0.00 100% completed  
30 WSS Chowgam Gundipora PHE 9.68 0.00 0 0.00 0.00 30% Completed (Proc. of pipes 100%, L/F=70%) Oct-20
31 Additional OHT  For WSS Kharman Ganesh PHE 30.00 7.45 6 15.17 7.45 100% Completed  
32 WSS Kralcheck PHE 35.00 26.82 7 28.48 26.82 100% Completed  
33 WSS Vessu Manigam PHE 44.32 8.78 3 9.68 8.78 80% Completed (Proc. of pipes 100%, L/F 90%, fencing=20%, SR=90%, Intake Chamber/Spring protection=30%) Oct-20
34 WSS Kraloo Kanchloo PHE 120.14 29.89 6 29.89 29.89 90% Completed (Proc. Of pipes=100%, L/F=80%, SR=70%) Oct-20
Total Qazigund Division   303.37 96.02 29 118.67 96.02    
G. Total    4526.82 803.14 207 1155.76 803.14    
Health Sector 
1 NTPHC Pariwan SICOP 154.48 101.53 1 101.53 101.53 50% Completed
(Truss with roofing completed)
Mar-21
2 NTPHC Manzgam SICOP 154.48 83.81 1 83.81 83.81 40% Completed:
(G.Floor slab laid) Brick work of 1st floor in progress
Mar-22
3 NTPHC Khull JKPHC 148.00 49.13 2 49.13 49.13 55%  Completed:
(First Floor slab laid & brick work and plaster work of G.floor completed, )
Mar-21
4 NTPHC Nandimarg JKPHC 148.00 53.40 2 53.40 53.40 50% Completed:
(Ist Floor slab laid, Truss laid & 1st floor brick work completed)
Mar-21
5 NTPHC Shamshipora JKPHC 168.00 72.11 1 72.11 72.11 Completed  
6 Construction of Addl. Accomodation PHC Frisal JKPHC 490.00 46.55 1 46.55 46.55 35% Completed
(1st floor column work completed)
Mar-22
7 PHC Devsar JKHB 162.59 0.00 0 0.00 0.00 75% completed:
(Building raised upto truss level & truss laid with roofing).
Mar-21
8 PHC Nihama JKHB 148.12 0.00 0 0.00 0.00 75% completed:
(Skeleton structure completed).
Mar-21
9 PHC K.B Pora JKPHC 375.00 86.32 1 86.32 86.32 25% completed
(Plinth Completed)
Mar-22
10 NTPHC Sadoora JKPHC 158.00 29.32 1 29.32 29.32 37% Completed:
(Brick work of first floor completed)
Mar-21
11 NTPHC Furrah SICOP 154.48 99.03 1 99.03 99.03 62% completed
 (Truss in progress)
Mar-21
12 NTPHC Nepora JKPHC 148.00 67.85 2 67.85 67.85 50% Completed
(G. Floor slab laid, work on 1st floor completed, Truss laid, Finishing in progress)
Mar-21
13 NTPHC Chowgam JKHB 94.78 0.00 0 0.00 0.00 building completed & roofed and finishing work in progress. Mar-21
Sub Total Health   2503.93 689.05 13 689.05 689.05    
PDD Sector 
1 Augmentation of 132/33 KV, Grid Station Kulgam KPCDL 366.16 0.00 3 0.00 0.00 85% completed. Jun-20
2 Construction of 33/11 KV 1×6.3 MVA at Receiving station Shamshipora   58.42 0.00 1 3.13 0.00 ROW issue, to be sorted by DDC, Anantnag   
3 Construction of 33/11KV 1×6.3 MVA 6.3 MVA receiving station at DH Pora Nagam Discom, Kashmir 113.66 0.00 0 0.00 0.00 60% work completed
Construction of receiving station yard in progress
Jun-20
4 Upgradation of DH Pora Transmission line, delinking of Nillow, Pariwan from Shopian/Pampore Grid to Kulgam Grid Discom, Kashmir 27.00 0.00 1 19.32 0.00 90% work completed Jun-20
Sub Total PDD   565.24 0.00 5 22.45 0.00    
Higher Education Sector 
1 Construction of Lecture Block & Auditorium at GDC Kulgam R&B 882.78 0.00 0 0.00 0.00 Tendering in progress  
Sub Total Higher Education   882.78 0.00 0 0.00 0.00    
School Education Sector 
1 Construction of 06 roomed additional accommodation at Govt HSS Munid Kulgam Edu. Deptt 64.86 28.71 2 40.17 28.71 Building roofed, finishing in progress May-21
2 Construction of 04 roomed additional accommodation at GHSS Kulgam Edu. Deptt 46.58 33.65 2 34.37 33.65  Finishing  in progress May-21
3 Construction of 04 roomed additional accommodation at HSS Areh Kulgam Edu. Deptt 47.09 26.70 2 27.33 26.70 Finishing  in progress May-21
4 Providing of water supply to 71 uncovered schools of Kulgam Edu. Deptt 33.10 0.00 0 0.00 0.00 Water supply to 70 schools completed   
Sub Total School Education   191.63 89.06 6 101.87 89.06    
Technical  Education Sector 
1 Completion of deficient infrstructure pointed out by AICTE in Govt Polytechnic Kulgam / College Cafetaria R&B 82.00 0.00 0 0.00 0.00 brick work in progress Jun-20
Sub Total Technical Education   82.00 0.00 0 0.00 0.00    
YSS Sector 
1 Development of playing field at Devsar Kulgam by way of construction of change room seating tiers, chain link fencing and earth work and cutting Sports Council 52.00 5.50 2 18.80 5.50 Chain fencing & earth work completed Dec-20
2 Construction of R/Wall at play field Devsar Sports Council 16.00 16.00 2 16.00 16.00 Completed  
3 Development of play field at Kilam Kulgam by way of leveling of ground construction of cricket pitches and construction of Mini-Pavillion & inbuilt sound system Sports Council 60.00 8.50 2 23.50 8.50 (Leveling completed) Jul-20
4 Dvelopment of play field at Parrigam Homeshali Bugh Kulgam Sports Council 149.00 44.00 2 44.00 44.00 52% Completed Jun-20
5 C/o Basket ball court at HSS DK Marg Sports Council 12.17 0.00 0 0.00 0.00 70% completed Aug-20
6 C/o Basket ball court Synthetic at HSS Manzgam Sports Council 30.50 0.00 0 0.00 0.00 20% completed Sep-20
7 C/o Badminton court Synthentic at HSS KB Pora Sports Council 8.00 0.00 0 0.00 0.00 Tendering in progress Sep-20
8 C/o Basket court synthetic at BHSS Kulgam Sports Council 30.50 0.00 0 0.00 0.00 Allotment under process Sep-20
9 C/o Cricket wicket net at BHSS Kulgam Sports Council 2.85 0.00 0 0.00 0.00 Completed  
10 C/o Volley Ball Court synthetic at BHSS Malwan Sports Council 14.88 0.00 0 0.00 0.00 Work alloted Jan-21
11 C/o Badminton court synthetic at GHSS Kulgam. Sports Council 8.00 0.00 0 0.00 0.00 Work alloted Sep-20
12 C/o roller skating ring at GHSS Kulgam Sports Council 8.00 0.00 0 0.00 0.00 AAA awaited Dec-20
13 C/o Hand ball court synthetic at HS Tarigam Sports Council 76.00 0.00 0 0.00 0.00 Work alloted but land issue Jan-21
14 C/o Badminto court concrete at BHSS Yaripora Sports Council 4.52 0.00 0 0.00 0.00 Completed  
15 C/o Badminton court concrete at HSS Frisal Sports Council 4.52 0.00 0 0.00 0.00 Completed  
16 C/o Basket ball court concrete at HS Noonmai Sports Council 12.17 0.00 0 0.00 0.00 land issue Dec-20
17 C/o Hand ball court synthetic at HSS Munandguffan Sports Council 76.00 0.00 0 0.00 0.00 Allotment issued but land issue Sep-20
18 C/o Volley Ball court synthetic at HS Hablish Sports Council 14.88 0.00 0 0.00 0.00 70% completed Dec-20
19 C/o Badminton court synthetic at HSS Chowgam Sports Council 8.11 0.00 0 0.00 0.00 Tendering in progress Sep-20
20 C/o Volley Ball court synthetic at HSS Devsar Sports Council 14.88 0.00 0 0.00 0.00 AAA awaited Dec-20
Sub Total YSS   602.98 74.00 8 102.30 74.00    
Irrigation Sector
1 Sonman Canal (57 Spots) Irrigation 407.04 258.26 57 307.84 258.26 100% completed  
Sub Total Irrigation Sector   407.04 258.26 57 307.84 258.26    
Animal & Sheep Husbandry Sector
1 Sheep Extension Centre at Kaddar Kulgam R&B 5.00 4.60 4 4.60 4.60 100% completed  
Sub Total Animal & Sheep   5.00 4.60 4 4.60 4.60    
H&UDD Sector
1 Community / Marriage Hall near Kulgaswari Temple at Kulgam H&UDD 53.41 13.76 1 13.76 13.76 70% completed
(G. Floor Slab laid) 
Jun-20
Sub Total H&UD   53.41 13.76 1 13.76 13.76    
Grand  17224.49 3418.93 333 3960.85 3418.93